Share via


<PercentWorkComplete> Element

For a <Task>, <PercentWorkComplete> is the current status of a task, expressed as the percentage of the task's work that has been completed.

For a <Resource>, it is the current status of all tasks assigned to a resource, expressed as the total percentage of the resource's work that has been completed.

For an <Assignment>, it is the current status of an assignment, expressed as the percentage of the assignment's work that has been completed.

Element Properties

Property Value
Data Type Integer
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Task
Resource
Assignment

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element

XML Schema for the <Resource> Element
XML Structure for the <Resource> Element

XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element