<WorkVariance> Element

For a <Task>, <WorkVariance> is the difference between a task's baseline work and the currently scheduled work.

For a <Resource>, it is the difference between a resource's total baseline work and the currently scheduled work.

For an <Assignment>, it is the variance of assignment work from the baseline work, expressed as minutes x 1000.

Element Properties

Property Value
Data Type Float
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Task
Resource
Assignment

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element

XML Schema for the <Resource> Element
XML Structure for the <Resource> Element

XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element