Share via


<Calendars> Element

The collection of calendars that is associated with the project.

Calendars are used to define standard working and nonworking times. A project must have one base calendar. Tasks and resources may have their own calendars, which are based on a base calendar.

Element Properties

Property Value
Data Type ComplexType
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints Sequence

Parent Elements

Project

Child Elements

Element Required/Optional Description
<Calendar> Required A calendar in the project.

See Also

XML Schema for the <Calendar> Element
XML Structure for the <Calendar> Element