TaskDependencies Property
Returns a TaskDependencies collection representing the link type and link lag information between two tasks. Read-only.
Example
This example examines each predecessor for the specified task and brings up a message for each predecessor that has a priority higher than "Medium."
Sub FindHighPriPreds()
Dim TaskDep As TaskDependency
For Each TaskDep In ActiveProject.Tasks("Write Requirements Brief").TaskDependencies
If TaskDep.From.Priority > 500 Then
MsgBox "Task #" & TaskDep.From.ID & " (" & TaskDep.From.Name & ") " & _
"has a priority higher than medium."
End If
Next TaskDep
End Sub
Applies to | Task Object, Tasks Collection Object
See Also | From Property | Lag Property | Predecessors Property | PredecessorTasks Property | Successors Property | SuccessorTasks Property | TaskDependency Object, TaskDependencies Collection Object | To Property