ProjectBeforeTaskChange Event

Occurs before the user changes the value of a task field.

Syntax

Private Sub object**_ProjectBeforeTaskChange(ByVal** tsk As MSProject.Task, ByVal Field As PjField, ByVal NewVal As Variant, Cancel As Boolean)

object     An object of type Application declared with events in a class module. For more information, see Using events with the Application object.

tsk     The task whose field is being changed.

PjField

pjTaskActualCost pjTaskHyperlinkSubAddress
pjTaskActualDuration pjTaskID
pjTaskActualFinish pjTaskIgnoreResourceCalendar
pjTaskActualOvertimeCost pjTaskIndex
pjTaskActualOvertimeWork pjTaskIndicators
pjTaskActualOvertimeWorkProtected pjTaskIsAssignment
pjTaskActualStart pjTaskLateFinish
pjTaskActualWork pjTaskLateStart
pjTaskActualWorkProtected pjTaskLevelAssignments
pjTaskACWP pjTaskLevelCanSplit
pjTaskAssignmentDelay pjTaskLevelDelay
pjTaskAssignmentUnits pjTaskLinkedFields
pjTaskBaseline1-10Cost pjTaskMarked
pjTaskBaseline1-10Duration pjTaskMilestone
pjTaskBaseline1-10DurationEstimated pjTaskName
pjTaskBaseline1-10Finish pjTaskNotes
pjTaskBaseline1-10Start pjTaskNumber1-20
pjTaskBaseline1-10Work pjTaskObjects
pjTaskBaselineCost pjTaskOutlineCode1-10
pjTaskBaselineDuration pjTaskOutlineLevel
pjTaskBaselineDurationEstimated pjTaskOutlineNumber
pjTaskBaselineFinish pjTaskOverallocated
pjTaskBaselineStart pjTaskOvertimeCost
pjTaskBaselineWork pjTaskOvertimeWork
pjTaskBCWP pjTaskParentTask
pjTaskBCWS pjTaskPercentComplete
pjTaskCalendar pjTaskPercentWorkComplete
pjTaskConfirmed pjTaskPhysicalPercentComplete
pjTaskConstraintDate pjTaskPredecessors
pjTaskConstraintType pjTaskPreleveledFinish
pjTaskContact pjTaskPreleveledStart
pjTaskCost pjTaskPriority
pjTaskCost1-10 pjTaskProject
pjTaskCostRateTable pjTaskRecurring
pjTaskCostVariance pjTaskRegularWork
pjTaskCPI pjTaskRemainingCost
pjTaskCreated pjTaskRemainingDuration
pjTaskCritical pjTaskRemainingOvertimeCost
pjTaskCV pjTaskRemainingOvertimeWork
pjTaskCVPercent pjTaskRemainingWork
pjTaskDate1-10 pjTaskResourceEnterpriseMultiValueCode20-29
pjTaskDeadline pjTaskResourceEnterpriseOutlineCode1-29
pjTaskDelay pjTaskResourceEnterpriseRBS
pjTaskDemandedRequest pjTaskResourceGroup
pjTaskDuration pjTaskResourceInitials
pjTaskDuration1-10 pjTaskResourceNames
pjTaskDuration1-10Estimated pjTaskResourcePhonetics
pjTaskDurationVariance pjTaskResourceType
pjTaskEAC pjTaskResponsePending
pjTaskEarlyFinish pjTaskResume
pjTaskEarlyStart pjTaskResumeNoEarlierThan
pjTaskEarnedValueMethod pjTaskRollup
pjTaskEffortDriven pjTaskSheetNotes
pjTaskEnterpriseCost1-10 pjTaskSPI
pjTaskEnterpriseDate1-30 pjTaskStart
pjTaskEnterpriseDuration1-10 pjTaskStart1-10
pjTaskEnterpriseFlag1-20 pjTaskStartSlack
pjTaskEnterpriseNumber1-40 pjTaskStartVariance
pjTaskEnterpriseOutlineCode1-30 pjTaskStatus
pjTaskEnterpriseProjectCost1-10 pjTaskStatusIndicator
pjTaskEnterpriseProjectDate1-30 pjTaskStop
pjTaskEnterpriseProjectDuration1-10 pjTaskSubproject
pjTaskEnterpriseProjectFlag1-20 pjTaskSubprojectReadOnly
pjTaskEnterpriseProjectNumber1-40 pjTaskSuccessors
pjTaskEnterpriseProjectOutlineCode1-30 pjTaskSummary
pjTaskEnterpriseProjectText1-40 pjTaskSV
pjTaskEnterpriseText1-40 pjTaskSVPercent
pjTaskEstimated pjTaskTCPI
pjTaskExternalTask pjTaskTeamStatusPending
pjTaskFinish pjTaskText1-30
pjTaskFinish1-10 pjTaskTotalSlack
pjTaskFinishSlack pjTaskType
pjTaskFinishVariance pjTaskUniqueID
pjTaskFixedCost pjTaskUniquePredecessors
pjTaskFixedCostAccrual pjTaskUniqueSuccessors
pjTaskFixedDuration pjTaskUpdateNeeded
pjTaskFlag1-20 pjTaskVAC
pjTaskFreeSlack pjTaskWBS
pjTaskGroupBySummary pjTaskWBSPredecessors
pjTaskHideBar pjTaskWBSSuccessors
pjTaskHyperlink pjTaskWork
pjTaskHyperlinkAddress pjTaskWorkContour
pjTaskHyperlinkHref pjTaskWorkVariance
pjTaskHyperlinkScreenTip  

NewVal     The new value for the field specified with Field.

Cancel     False when the event occurs. If the event procedure sets this argument to True, the value for the field specified with Field is not changed.

Remarks

Microsoft Office Project 2003 events do not occur when the project is embedded in another document or application.

The ProjectBeforeTaskChange event doesn't occur when timescaled data changes, when constraint data in the Task Details Form changes, when a task is split by manipulating its task bar on the Gantt Chart, when changes are made to outline level or outline number, when a baseline is saved, when a baseline is cleared, when an entire task row is pasted, during resource pool operations, when inserting or removing a subproject, or when changes have been made using a custom form.

Example

This example informs the user when a task's duration increases and by how much. This example requires a new class module and additional code for it to have an effect. For more information, see Using events with the Application object.

Private Sub App_ProjectBeforeTaskChange(ByVal tsk As Task, ByVal Field As PjField, _
    ByVal NewVal As Variant, Cancel As Boolean)
    
    Dim TaskDuration As Long

    TaskDuration = Val(NewVal) * 480    ' Convert days to minutes

    If Field = pjTaskDuration And TaskDuration > tsk.Duration Then
        If (TaskDuration - tsk.Duration) \ 480 < 1 Then
            MsgBox "The task " & Chr$(34) & tsk.Name & Chr$(34) & " is now " & _
                (TaskDuration - tsk.Duration) / 480 & (TaskDuration - tsk.Duration) \ 480 & _
                    " day(s) longer."
        Else
            MsgBox "The task " & Chr$(34) & tsk.Name & Chr$(34) & " is now " & _
                (TaskDuration - tsk.Duration) / 480 & " day(s) longer."
        End If
    End If
End Sub